2019 Begins, Tanjung Selor Type B Hospital Completed 2020

The plan for the construction of a Type B Referral Hospital in Tanjung Selor, Bulungan Regency is close to realization. At present the process has arrived at the design review stage or reviewing designs that have been made beforehand. This is done, because the location of the hospital construction is moving or changing.

As is known, previously the hospital, which was funded through a loan from PT Sarana Multi Infrastruktur (SMI) worth Rp 340 billion, was planned to be built in a location not far from Tanjung Selor Hospital. Due to several considerations, the location was moved to Kilometer 4 Km on Trans Kalimantan Road (Selel Selel).

The Governor of North Kalimantan (Kaltara) Dr H. Irianto Lambrie said, according to information from the Public Works, Spatial Planning, Housing and Settlement Areas (DPUPR-Perkim) of Kaltara Province, it was targeted that the RS design review activities would be completed in September.

After completion, the Governor continued, accompanied by the Head of DPUPR-Perkim Kaltara Suheriyatna, the pre-contract or auction process will only be conducted. Meanwhile, for the signing of the contract, according to the target will be carried out in early November. “All tender documents are ready. Starting from the permit documents from the North Kalimantan Provincial DPRD, the Ministry of Home Affairs (MOHA), the Ministry of Finance (Ministry of Finance). Including from PT SMI, as the lender,” Irianto said.

“We only have to wait for the results of the design review from the consultants. God willing, the beginning of September will be completed. And proceed with the auction process. So that in early 2019 we can start construction activities,” he continued.

In addition to conducting design reviews, the construction of Tanjung Selor Referral Hospital itself has carried out work, road opening and land maturation. For road opening activities using Special Allocation Funds (DAK). With a ceiling value of Rp. 28 billion for a road length of 40 kilometers and a width of 40 meters. Road opening is carried out in two directions. Namely from the direction of Tanjung Selor to Kilometer 4. And from the direction of kilometer 4 towards Sajau. “The opening of this road, as well as to open connectivity leads to Tanah Kuning,” explained Irianto.

Meanwhile, for land maturation, use the Provincial Budget (APBD) of Rp. 3 billion, and it has been completed. “This is done, so that when the work contract is done, the land is ready,” the Governor explained.

Back to List News

Related News

Geo Dipa-SMI Develops Dieng Geothermal Power Plant Inaugurated Konawe Hospital, Sri Mulyani: Tax Money is Returned to The People PT Sarana Multi Infrastruktur Expands Sector for Its Financing Bogor Outer Ring Road Toll Project Got Finance from SMI IDR 660 Billion Visiting the Sorik Marapi Geothermal Project